Crossing under the Rio Grande

PUMPCO completes last leg of the Impulsora Pipeline

In Webb County, Texas, near Laredo, a nine-person directional drilling crew with PUMPCO, Inc. have successfully crossed under the Rio Grande into Mexico. The project involved boring and pulling back 2200 feet (670.6 m) of 36-inch (91.4-cm) pipe approximately 80 feet (24.4 m) under the river’s bed. It was the last leg of the 17-mile (27.4-km) long Impulsora Pipeline which will soon transport 504,000 MMBtu of natural gas per day across the border into Mexico.

The Impulsora Pipeline is part of the Nueva Era joint venture between Howard Energy Partners (HEP) and Grupo Clisa. Nuevo Era is responsible for designing, constructing and operating a pipeline system to transport supplies from the United States to end users in and around Monterrey, Mexico. The project involves the construction of two pipelines — on the U.S. side of the border in Webb County is the Impulsora Pipeline, and in Mexico, there are the 171 miles (275.2 km) long Midstream de Mexico. Nueva Era will provide seamless service to shippers wishing to transport on both pipelines. Impulsora received its Presidential Permit on May 14, 2015, to construct, operate and maintain border-crossing facilities.

Installing the pipeline

PUMPCO, Inc. in Giddings, Texas, is the lead contractor for the bulk of the construction on the Impulsora Pipeline. With a workforce of approximately 1,800 people, PUMPCO is an industry leader in pipeline construction and has installed thousands of miles of pipe throughout Texas and other states.

PUMPCO’s crews started construction of the pipeline by using a combination of open-cutting methods and horizontal directional drilling (HDD).

According to Adam Nietsche, operations manager for PUMPCO, laying the 36-inch (91.4-cm) pipeline in Webb County went as easily and quickly as it could. “We used open trenches for the bulk of the work, but we also had some areas that called for horizontal directional drilling,” he says. “We had a total of four drills working on the project, including a Vermeer D1000x900 Navigator® horizontal directional drill which we used to make the shot under the Rio Grande. That was the machine we determined was the best choice for this project from our fleet of 22 HDD rigs.”

The Vermeer D1000x900 horizontal directional drill is one of five Vermeer maxi rigs in PUMPCO’S fleet. The D1000x900 is equipped with twin Caterpillar C27 ACERT engines that produce a maximum of 92,000 ft-lb (124,735.3 Nm) of rotational torque and 1,000,000 pounds (4,448 kN) of thrust/pullback. With high-torque, low-speed Hägglunds hydraulic motors powering the rotary and carriage drives, the D1000x900 drill runs full torque and full rotary rpm simultaneously. Also, a floating vice allows the breakout system to clamp the full rod upsets during breakout of the lower and upper joints to help prevent rod wrap or windup.

Nietsche says the pipeline industry has shifted to an increased number of horizontal directional drills per project. “A successful drill project incorporates a variety of support equipment from cleaning units, water tanks, mud pumps, vacuum trucks, generators, drill strings and many others,” he adds. “Our team leverages this equipment to make certain each project is on schedule and completed in a timely manner.”

Border crossing

With miles of pipeline in place in Webb County, there was one major obstacle standing in the way of connecting the two pipelines — boring underneath the Rio Grande. To perform the bore, PUMPCO set up its equipment on the U.S. side of the river, right outside Laredo. The pipe was waiting for them to pull back on the Columbia, Mexico, side of the river. Once the product pipe was pulled into place, it would be capped and lay in waiting for the Midstream de Mexico pipeline to be connected.

“To complete the bore, we needed the members of our team on the U.S. and Mexico sides of the river every day,” explains Nietsche. “Many of our crew members had to cross back and forth multiple times a day, along with equipment. Luckily, the bore took place 10 minutes away from the nearest border crossing, but working on a job that involves two countries is always a little more challenging.”

PUMPCO’s crew used radios and some of the latest advances in locating equipment to ensure that the river and the border didn’t stand in its way of successfully making the cross.

Job details

The 2200-foot (670.6-m) bore called for the crew to drill 80 feet (24.4 m) below the river bed and come up on the other side. Overseeing the onsite operations was Jason Walton, PUMPCO site foreman. “We’ve completed two other bores under the Rio Grande before this one, and we’ve found that changes in the soil can be pretty dramatic, going from sand to rock, back to sand within a matter of a few feet,” he explains.

To reach the desired depth, the crew positioned the D1000x900 directional drill to start the pilot bore at an 8-degree angle and exited on the other side at 6 degrees. Throughout the bore, crews needed to maintain a 3600-foot (1097.3-m) bend radius to make pullback of the 36-inch (91.4-cm) pipe possible.

Walton says they selected the Vermeer D1000x900 directional drill because of the distance they had to drill and the size of the product they were pulling back. For locating, PUMPCO’s crews used a Tensor Steering Tool System that uses a grid of magnetically charged wires to determine the location of the drill housing.

The pilot bore

With all the equipment in place, PUMPCO’s crew got started with the initial pilot bore using an 8 1/- inch (21.6-cm) barrel chisel bit. “In that first pass, we ran into a little bit of everything: sand, rock, cobble and gravel,” says Walton. “Honestly, the pilot bore took us longer than we first thought it would, but as we were coming through those different layers of material, we either needed to speed up or slow down our drilling speed. In sand, we went a little faster to avoid digging in, and then we slowed down for rock, gravel and cobble. It was a challenge.”

Widening the hole

Before pulling back the pipelines, the crew needed to widen the hole to 48 inches (121.9 cm). “We started with a 20-inch (50.8-cm) rock reamer, then stepped it up from there with a 28-inch (71.1-cm), 36-inch (91.4-cm) and then 42-inch (106.7-cm) reamer. The final pass we made was with a 48-inch (121.9-cm) reamer before pulling back the pipeline into position,” explains Walton.

On average, the crew drilled around 500 feet (152.4 m) a day, so each pass took them around four and a half days to complete.

Walton says the crew was running a 110-115-viscosity mud mixture throughout the process, which was primarily bentonite. PUMPCO’s crew used a similar mixture on its other two Rio Grande crossings.

With every pass, the PUMPCO crew got closer to finally being able to pull back product. In total, around a month was spent widening the bore path to 48 inches (121.9 cm) in diameter.

Finishing the job

When the crew finally completed its last pass with a reamer, crews hooked a 1.3 million-lb (589,670 kg) swivel onto the drill string and the wielded-together pipeline waiting for them on the Mexico side of the river. Pulling back the pipe only took the crew around a day to complete. The 2200 feet (670.6 m) of pipe was connected to the 17 miles (27.4 km) laid by PUMPCO’s other crews. After that, Walton and his crew packed up the equipment and got ready to move on to the next challenging job.

Nietsche and Walton are happy to have another successful Rio Grande crossing out of their way. “Having trained and experienced crews, along with investing in high-quality equipment, are the keys to taking on projects like this,” explains Nietsche. “We pride ourselves on having the best people and the best equipment; that’s what has helped us earn the reputation of being an industry leader in pipeline construction.”

No matter how many river crossings a crew has done, completing that final pullback is a good feeling. As pipeline industry experts, PUMPCO knows what it takes to accomplish a job of this magnitude. The company invests in its people and provides them with quality equipment, to help ensure jobs are completed on time and on budget.

Vermeer and Navigator are trademarks of Vermeer Manufacturing Company in the U.S. and/or other countries. Caterpillar and ACERT are trademarks of Caterpillar Inc. Häglunds is a trademark of Bosch Rexroth AG.

© 2017 Vermeer Corporation. All Rights Reserved.

Get the latest news delivered right to your inbox.

Subscribe Now

Related News Articles

Embracing vacuum excavation for rural water line repair: A BCWA case study

Bear Creek Water Association is harnessing vacuum excavation for efficient underground water line repair. This innovative method is swiftly becoming indispensable for municipalities and rural water associations. Read on to understand why you need to consider this for your utility maintenance and repair strategies.

Read More

How Tracksons Drilling achieves decades of success with dealership support

Wondering if partnering with Vermeer could be a good fit for your business? See how an Australian-based underground contractor has grown their fleet and exceeded customer expectations by working closely with their local Vermeer dealer.

Read More

Maximizing productivity in solar construction with technology and the right equipment

GPS technology in solar construction addresses labor shortage challenges and enhances efficiency. The integration of GPS in equipment like the Vermeer PD10R pile driver reduces surveying costs, proving a revolutionary step for the solar construction industry.

Read More