6 steps to help prevent cross bores

Don’t take shortcuts when it comes to locating utility lines before beginning HDD work

There’s no room on a horizontal directional drilling (HDD) jobsite for shortcuts. That’s especially true when it comes to preventing cross bores. Doing so takes planning, time, attention to working conditions and the right tools. But failing to do so can have major consequences for HDD operators and residents and interrupt the function of private and public utility lines.

A cross bore is an unintentional intersection between two or more underground utility lines. They can be dangerous and expensive, both during and after the job is completed. Preventing cross bores starts well before work begins. First, emphasize to operators and crew members that an HDD jobsite is no place for shortcuts with prior preparation or operation.

Follow these steps

Once operational protocols are set and crews commit to following them, the first step to starting a job is locating any existing underground utility lines. Start with these steps before you even turn a wheel:

  1. Call your state’s 811 center to have underground utility lines marked on the surface ahead of time.
  2. Consult with property owners — commercial, municipal or residential — to determine if there are any private utility lines on the jobsite.
  3. Use tools like Vermeer Projects to enable you to work with your operator to plan and map each job, and communicate progress, job logistics and operating conditions while on the job.
  4. Calibrate your drill head transmitter and allow ample space between underground lines.
  5. Conduct a jobsite walk-through to look for evidence of any other utility lines or infrastructure. If there are any signs of other potential buried utilities, use another locator system like ground-penetrating radar to confirm any other suspected lines.
  6. Double-check all utility locates before beginning work.

Watch closely during operation

Once you begin HDD work, the operator should remain watchful for any signs of cross bores, stopping to pothole where drilling could intersect with existing utility lines. Doing so is required by law and will help ensure the excavation is completed without issue.

Upon completion of the job, document the bore path so it’s available for reference and future work crews can verify utility line locations prior to conducting any underground work.

Get the latest news delivered right to your inbox.

Subscribe Now

Related News Articles

Moss tops Solar Power World ranking, breaks company record using Vermeer pile drivers

Solar contractor Moss had a huge July, and Vermeer pile drivers helped power the way.

Read More

Brewer Water Department tackles lead service line inventory with vacuum excavation

Brewer Water Department tackles EPA lead service line inventory requirements with innovative vacuum excavation technology. Discover how this efficient approach minimizes disruption and improves infrastructure while meeting regulatory demands.

Read More

Why the d100x140 s3 hdd is still the one for west Texas boring

After building a unique boring machine in his spare time at the age of 60, Bill Harrington started the company in 1975. The rest is history. Built on innovation, reliable equipment helps West Texas Boring thrive in the most extreme conditions.

Read More